June 7th- doors and carpet installed. Had a courtesy inspection with the city of Gilbert to make sure we didn’t have any problems during final inspection later in the week. Discussed hardware requirements, final signage, exiting ….

June 8th- passed final sprinkler inspection, passed final fire inspection. Door hardware installed

June 8th – OSA set and passed early AM. Passed final building inspection, went very quick because we had passéd all the other inspections earlier in the week and the inspector had seen the project two days before

June 9th- touch ups started