by Colin Merrill | Apr 23, 2026 | Updates
Scottsdale Family Dental’s expansion is moving through the MEP rough-in phase on schedule. Drywall is hung throughout the new operatory rooms and corridor, and the ceiling above is a fully coordinated layer of sheet metal ductwork, insulated flex duct drops,...
by Colin Merrill | Apr 21, 2026 | Updates
Millwork installation is well underway at our Factory Motor Parts tenant improvement in Phoenix, as this warehouse flex space moves into its final finish-out phase. BCW Inc. is on-site setting a full suite of custom cabinetry throughout the office wing — upper wall...
by Colin Merrill | Apr 14, 2026 | Updates
Paving and site work is underway at the UTV Stereo Expansion in Mesa. The crew is laying fresh asphalt across the parking lot while new concrete curbing is set at the building perimeter, landscaped islands, and ADA-compliant entrance...
by Colin Merrill | Apr 9, 2026 | Updates
Emerald Inc. recently completed a tenant improvement for EDCO at 2120 W. Guadalupe Road, Suite 1 in Gilbert, Arizona. The project converted existing industrial flex space into a fully built-out corporate office, including private office suites with black aluminum...
by Colin Merrill | Mar 26, 2026 | Updates
The UTV Stereo expansion in Mesa is moving fast. The CMU block walls on the new 10,000 square foot addition are complete, with window and door openings framed and ready for the next phase. Outside, fresh concrete flatwork has been poured along the building perimeter...
by Colin Merrill | Mar 23, 2026 | Updates
Painting is underway at our Factory Motor Parts tenant improvement in Phoenix. The team is finishing new interior partition walls this week, with protection in place to keep the active warehouse operational throughout...