The asphalt was placed for the parking lot on June 3rd and has been closed until the morning of June 10 to cure.

The building electrical was trimmed out and light fixtures installed. Additionally, fire alarm wiring, mechanical and above ceiling plumbing was all passed by the City Inspector.

Ceiling tile was all installed and trim out of the fire sprinklers was completed.

Fire alarm panel and related equipment are installed with the exception of a few horn strobes which will be completed the week of June 13th.

The floor was prepped and 90% of field tile has been installed. The floor tile cuts at doorways and around the walls began Saturday June 11th.