by Colin Merrill | Jan 19, 2021 | Updates
Rough grading and excavation for plumbing trenches is happening today at Apple Valley Dental and...
by Colin Merrill | Jan 18, 2021 | Updates
Stem panel forms have been stripped at Apple Valley Dental & Braces, and our plumber has laid out for excavation of underground...
by Colin Merrill | Jan 18, 2021 | Updates
The stem wall was poured at Apple Valley Dental &...
by Colin Merrill | Jan 18, 2021 | Updates
In preparation for doors, door frames and side light frames are being installed at Fusion power. We are also installing ceiling tiles around the perimeter of the...
by Colin Merrill | Jan 14, 2021 | Updates
Work continues on the stem wall forms at Apple Valley Dental. We should pass inspections & pour...