Priority Hearing (an audiologist clinic) is at the following point:

Rough electrical, plumbing, fire alarm wiring, fire sprinklers at hard ceilings and framing are completed.

Both the Pinal Inspector and the Rural Metro Fire Department have inspected the project and approved
The framing and we are ready for sheet rock.

Dr. Anderson and his wife have approved the soffit along with the data and power locations.

All sheetrock, insulation and joint compound are stocked on the job as of today and Superior Drywall is scheduled to begin Tuesday unless they can get a crew for Monday of next week. We are scheduled to have sheetrock and insulation completed by 9-15-16, with county inspection on that day or the following day.

BCW for the millwork and JTG for counter tops have been informed of schedule and are prepared field measure.

Heard Acoustics is scheduled to place grid on 9-21-16, provided all pre-requisites have been completed.

Quality Floors is scheduled to do the tile in the restroom on the 28th and the remainder of the floors on the 29th.