by Colin Merrill | Oct 28, 2020 | Updates
Painting continues at this Nascent Health Clinic buildout in...
by Colin Merrill | Oct 27, 2020 | Updates
Here are some progress photos of the paint at Ruby Bloom Boutique in Queen...
by Colin Merrill | Oct 22, 2020 | Updates
This stucco repair is coming along nicely, take a look at the...
by Colin Merrill | Oct 22, 2020 | Updates
Carpet Demo is completed on phase 3 at EMC Insurance. The Hufcor door track and ceiling repairs have been completed for the folding partition wall...
by Colin Merrill | Oct 22, 2020 | Updates
Electrical outlets with USB ports are going in at the Nascent Health IV treatment stations. Sometimes you run into a furred out demising wall full of hardened foam insulation, so you gotta cut some drywall. We patched the area afterward....
by Colin Merrill | Oct 22, 2020 | Updates
Major AC work happening out at Ruby Bloom! Drywall was textured and the office space is almost ready for paint....