Here are the progress photos from the job as of today. We still need to do a little touch up paint and waiting for the stucco screen wall at the street to cure enough to paint. We also will clean the storefront and windows this week. By the end of this week we hope to...
Week of June 20th: Roofers are 100% completed including punch list. Plumbers are all trimmed out and punch list is complete. Electrician’s are complete including punch list. National is complete with fire sprinklers and has been signed off by City Fire...
HVAC equipment was started and balanced. Tile floors were completed and grouted. Standing metal seam roof reached about 30% completion. The parking lot striping and signage was installed. Pre construction meeting for the Landscaping requested by the City was conducted...
June 7th- doors and carpet installed. Had a courtesy inspection with the city of Gilbert to make sure we didn’t have any problems during final inspection later in the week. Discussed hardware requirements, final signage, exiting …. June 8th- passed final...
Recent Comments